Monthly Progress Report

Monthly Progress Report Till August 2021

Uttar Pradesh Project Corporation Limited, Lucknow

Updated status of Prison Department Works
S.N. Month Target Completed Transferred
Till November 2020 29 9 22
December 2020 17 8 8
January 2021 17 9 4
February 2021 Target 19 12 1
March 2021 6 0 2
June 2021 3 1 0
Total 91 39 37

Lakshya 29, etc. by November 2020 | Lakshya 17, etc. by December 2020 | Lakshya 17, etc. by January 2021 | Lakshya 19, etc. by February 2021 | Lakshya 06, etc. by March 2021 | Lakshya 03, etc. by June 2021 |

Name of District
Agra, Prayagraj, Bulandshahar, Firozabad, Peelibhit, Kanpur Dehat, Hamirpur, Banda, Bijnaur, Gajipur, Eta, Raibareily, Jhansi, Sitapur,Hardoi, Varanasi, Mau, Fatehgarh, Gonda, Baliya, Mathura, Pratapgarh, Bareilly, Aligarh

Uttar Pradesh Project Corporation Limited, Lucknow

Updated status of Home Department Running Works
S.N. Description of Work Number of Unit
Total Number of Works 36
Works that have been transferred. 08
Completed work list that remains to be transferred 01
Such works whose advance instalment remains 13
Number of work to be reviewed 01
Number of works interrupted due to court stay 00
Such work whose money to be refunded 00
Fire Station (Residential/Non- Residential) Building 11
Fire Station Center in Lambhuwa, Distt. Sultanpur 01
Sewer Line in P.A.C. 4th of District Prayagraj 01